This week in Yancey County Schools, progress continues in many construction and renovation projects. At East Yancey Middle School, a crane was used to set the new chiller in place behind the building. Inside the building, complete demolition of the kitchen and student bathrooms was finished. Asbestos tile was removed in the east wing and work continues on the new ceiling grid.


At South Toe Elementary, painters are continuing to freshen up classrooms and demolition of student bathrooms is almost complete.


At Burnsville Elementary, the drainage system along the western side of the property is complete and grading work continues to prep for the new building site.